Case Study
32-Bed Military Hospital
Operational hospital delivered from excavation to readiness in less than 50 days during the COVID-19 emergency.
Full EPC delivery by SIPANEL — engineering, procurement, and construction.Case Study
Project snapshot
Project challenge
During the COVID-19 emergency, a fully operational 32-bed military hospital was needed from excavation to readiness in under 50 days, requiring full EPC coordination.
- Schedule overrun beyond 50-day target
- Coordination failures across EPC disciplines
- Envelope weather protection delays
- Internal partition installation bottlenecks
Engineering decision
SIPANEL delivered the complete project scope including engineering, shop drawings, excavation, construction, sandwich panel envelope, internal partitions, and full installation readiness.
Engineering teams coordinated full EPC delivery — from excavation and structural construction to sandwich panel envelope, internal partitions, and final readiness — within an emergency timeline.
Selected system logic placeholder for Sandwich Panel Systems.
Coordination note pending verified shop drawings, procurement files, and site notes.
Execution detail
Installation sequence
Execution followed a compressed 50-day schedule covering excavation, construction, sandwich panel cladding, internal partitioning, and installation to operational readiness.
Procurement control
Procurement control pending verified bill of materials and accessory scope.
Coordination with site team
Site coordination pending verified project communication records.
Quality checkpoints
- Drawing approval status pending
- Material and accessory list pending
- Installation inspection records pending
Measured result
Risks controlled before publication
Schedule overrun beyond 50-day target
Compressed scheduling with daily coordination across engineering, procurement, and execution teams.
Coordination failures across EPC disciplines
Integrated EPC management from excavation to final handover, eliminating coordination gaps.
Envelope weather protection delays
Controlled sandwich panel installation for roof and walls following an engineered timeline.
Internal partition installation bottlenecks
Coordinated interior partition sequencing with structural and MEP teams to prevent bottlenecks.